Estimation and Costing MCQs | Estimation and Costing Multiple Choice Questions and Answers

(1) The rate of an item of work depends on
[A] Proportion of mortar
[B] Specifications of materials
[C] Specifications of works
[D] All the above
Answer: All the above
(2) The plinth area of a building not includes
[A] Lift and wall including landing
[B] Area of cantilevered porch
[C] Internal shaft for sanitary installations up to 2 sq m. in area
[D] Area of the walls at the floor level
Answer: Area of cantilevered porch

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

Article and Schedule Quiz Start Test!
(3) A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
[A] 1500 m3
[B] 2000 m3
[C] 500 m3
[D] 1000 m 3
Answer: 1500 m3
(4) The brick work is not measured in cu m in case of
[A] Half brick wall
[B] Reinforced brick work
[C] One or more than one brick wall
[D] Brick work in arches
Answer: Half brick wall
(5) Pick up the correct statement from the following:
[A] The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
[B] The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
[C] The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
[D] All the above
Answer: All the above
(6) The cross -sections for a highway is taken at
[A] Intermediate points having abrupt change in gradient
[B] Right angle to the centre line
[C] 30 metres apart
[D] All the above
Answer: All the above
(7) The area of the cross-section of a road fully in banking shown in the given figure, is
[A] [sb² + r² (2bd + sd)²]/(r – s)
[B] [sb² + r² (2bd + sd)²]/(r² – s5)
[C] [sb² + r² (2bd + sd)²]/(r² – s²)
[D] None of these
Answer: [sb² + r² (2bd + sd)²]/(r² – s²)
(8) The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as
[A] Surface excavation
[B] Surface dressing
[C] Excavation
[D] Cutting
Answer: Surface excavation
(9) For the construction of buildings, the subheads of the estimate are
[A] Brickwork Flooring, Wood work, Steel work
[B] Earthwork, Concrete work, Brick work
[C] Brickwork, Stone work, Roofing
[D] All the above
Answer: All the above
(10) The expected out turn of 12 mm plastering with cement mortar is
[A] 8.0 sq m
[B] 2.5 sq m
[C] 4.0 sq m
[D] 6.0 sq m
Answer: 8.0 sq m
(11) The measurement is made for stone work in square metre in case of
[A] Wall facing
[B] Columns, lintels, copings
[C] Building work
[D] A. and D. of the above
Answer: A. and D. of the above
(12) The correct Prismoidal formula for volume is
[A] D/3 [first area + last area + 4 Even area + 2 odd areas]
[B] D/6 [first area + odd areas]
[C] D [first area + last area + Even area + 2 odd areas]
[D] None of above
Answer: D/3 [first area + last area + 4 Even area + 2 odd areas]
(13) Pick up the incorrect statement from the following:
[A] Cubic contents are measured to the nearest 0.1 cum
[B] Weights are measured to the nearest 0.001 tonnes
[C] Dimensions are measured to the nearest 0.01 m
[D] Areas are measured to the nearest 0.01 sq.m
Answer: Cubic contents are measured to the nearest 0.1 cum
(14) The order of booking dimensions is
[A] Height, breadth, length
[B] Breadth, length, height
[C] Length, breadth, height
[D] None of these
Answer: Length, breadth, height
(15) period in a septic tank is assumed The detention
[A] 20 minutes
[B] 30 minutes
[C] 40 minutes
[D] None
Answer: 30 minutes
(16) Pick up the item of work not included in the plinth area estimate
[A] Courtyard area
[B] Wall thickness
[C] Room area
[D] W.C. area
Answer: Courtyard area
(17) Pick up the item whose weight is added to the weight of respective item, is
[A] Bolts
[B] Cleats
[C] Brackets
[D] All the above
Answer: All the above
(18) The brick work is measured in sq metre, in case of
[A] Half brick walls or the partition
[B] Honey comb brick work
[C] Brick flat soling
[D] All the above
Answer: All the above
(19) The item of steel work which is measured in sq.m, is
[A] Ventilators and glazing
[B] Rolling shutters
[C] Collapsible gates
[D] All the above
Answer: All the above
(20) The volume is measured correct to the nearest
[A] 0.04 cum
[B] 0.02 cum
[C] 0.03 cum
[D] 0.01 cum
Answer: 0.01 cum

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!