A PERT project network consists of 5 activities A to E. The time estimates of these activities follow Beta-distribution

A PERT project network consists of 5 activities A to E. The time estimates of these activities follow Beta-distribution

Q. A PERT project network consists of 5 activities A to E. The time estimates of these activities follow Beta-distribution. The predecessor–successor (P-S) relationships between the nodes and time estimates of activities are given in table

ActivityP-SOptimistic time (days)Most likely time (days)Pessimistic time (days)
A1 – 2246
B2 – 34512
C2 – 45811
D3 – 52508
E4 – 54614

The variance (in days) of the critical path is            _ (round off to 2 decimal places)

Ans:

Sol:

Gkseries: Gkseries.com is a premier website to provide complete solution for online preparation of different competitive exams like UPSC, SBI PO, SBI clerical, PCS, IPS, IAS, IBPS PO, IBPS Clerical exam etc. & other graduate and post-graduate exams. Learn more on about us page