For an activity, ‘optimistic time duration’ is 4 days, ‘pessimistic time duration’ is 11 days and ‘most-likely time duration’ is 8 days

For an activity, ‘optimistic time duration’ is 4 days, ‘pessimistic time duration’ is 11 days and ‘most-likely time duration’ is 8 days

Q. For an activity, ‘optimistic time duration’ is 4 days, ‘pessimistic time duration’ is 11 days and ‘most-likely time duration’ is 8 days. The PERT value of time duration is________days

Ans: 7.8 to 7.9

PERT value of time duration/Expected time (te)

Gkseries: Gkseries.com is a premier website to provide complete solution for online preparation of different competitive exams like UPSC, SBI PO, SBI clerical, PCS, IPS, IAS, IBPS PO, IBPS Clerical exam etc. & other graduate and post-graduate exams. Learn more on about us page