The layout for an AGV system is shown in figure. The loading time is 0.5 minutes and the unloading time is also 0.5 minutes

The layout for an AGV system is shown in figure. The loading time is 0.5 minutes and the unloading time is also 0.5 minutes

Q. The layout for an AGV system is shown in figure. The loading time is 0.5 minutes and the unloading time is also 0.5 minutes. All distances are in meters.

Considering a vehicle velocity of 50 m/min, availability of 0.95 and traffic factor of       0.9,      the         number of vehicles required to satisfy a demand of 50 delivery/hour is     

Ans: 4-5

Sol: