Q. Processing times (including setup times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is____________________(correct to two decimal places).

JobProcessing time (days)Due date (days)
A38
B716
C44
D918
E517
F1319

Ans: 6.31 – 6.35