Processing times (including setup times) and due dates for six jobs waiting to be processed

Processing times (including setup times) and due dates for six jobs waiting to be processed

Q. Processing times (including setup times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is____________________(correct to two decimal places).

JobProcessing time (days)Due date (days)
A38
B716
C44
D918
E517
F1319

Ans: 6.31 – 6.35

Scroll to Top