Q.

Developed by the Special Projects Office of the U.S. Navy; this technique was first formally applied to the planning and control of the Polaris Weapon System in 1958 and worked well in expediting the completion of that programme. The technique is known as

[A] Gantt Chart
[B] PERT
[C] CRM
[D] Milestone budgeting
Answer & Explanation

Answer: PERT