Commerce Short Question | Gkseries

Q.

Which one of the following statements is true about estimated costs and standard costs ?

[A] Standard costs are based on scientific analysis and engineering studies while estimated costs are based on historical basis.
[B] Standard cost emphasis is on “what cost will be” while estimated cost emphasis is on “what cost should be”.
[C] Standard costs are more frequently revised compared to estimated cost.
[D] Estimated costs are more stable than standard costs
Answer & Explanation

Answer: Standard costs are based on scientific analysis and engineering studies while estimated costs are based on historical basis.

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

Article and Schedule Quiz Start Test!

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!