61 Pick up the correct statement from the following:
[A] The bending of bars near supports is generally at 45°
[B] The bent up bars at a support resist the sharing force
[C] The bent up bars at a support resist the negative bending moment
[D] All the above
Answer: All the above
62 The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is
[A] (6 + 12) chains
[B] (6 + 18) chains
[C] (6 + 15) chains
[D] None of these
Answer: (6 + 12) chains

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

Article and Schedule Quiz Start Test!
63 Pick up the correct statement from the following:
[A] All pipes are measured along the centre line of the pipes in metres
[B] All pipes and fittings are classified according to their diameters
[C] The diameter of the pipes is the nominal diameter of internal bore
[D] All the above
Answer: All the above
64 Pick up the correct statement in case of water supply.
[A] Pipes are classified according to their sizes and quality
[B] Cutting through walls and floors are included with the item
[C] Pipes laid in trenches and pipes fixed to walls are measured separately
[D] All the above
Answer: All the above
65 The total length of a cranked bar through a distance D. at 45° in case of a beam of effective length L, is
[A] L + (2 × 0.42 d)
[B] L – (0.42 d)
[C] L – (2 × 0.4 d)
[D] L + 0.42 d
Answer: L + (2 × 0.42 d)
66 If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is
[A] Bd + Sd2
[B] ½ (Bd + Sd2)
[C] B × d – Sd1/2
[D] B + d + Sd
Answer: Bd + Sd2
67 The minimum width of a septic tank is taken
[A] 75 cm
[B] 90 cm
[C] 70 cm
[D] 80 cm
Answer: 75 cm
68 For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
[A] 0.274 m3
[B] 0.247 m3
[C] 0.200 m3
[D] None of the above
Answer: 0.274 m3

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!