(1) The basic difference between MRP and MRP-II is:
[A] Finance
[B] Capacity Planning
[C] Bom
[D] Inventory
Answer: Finance
(2) Bill of material structure is used to
[A] calculate man power requirements
[B] calculate due dates
[C] calculate net requirements
[D] all of the mentioned
Answer: calculate net requirements

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

Article and Schedule Quiz Start Test!
(3) CRP takes material requirements from MRP and converts to
[A] standard hours of load
[B] standard hours of machine
[C] standard hours of man power
[D] all of the mentioned
Answer: insensitive
(4) Capacity planning is concerned with
[A] how much labour required
[B] how many machines required
[C] all of the mentioned
[D] none of the mentioned
Answer: all of the mentioned
(5) MRP-II system is called a closed loop system because it considers
[A] finance
[B] man power
[C] inventory
[D] none of the mentioned
Answer: finance
(6) For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be
[A] 500
[B] 1000
[C] 300
[D] none of the above
Answer: 500
(7) What does QA and QC stand for?
[A] Quality Adjustment and Queuing control
[B] Quality Assurance and Quality control
[C] Quality Adjustment and Quality completion
[D] Quality Assurance and Queuing Control
Answer: Quality Assurance and Quality control
(8) Which of the following option involves material and component control?
[A] Quality control
[B] Feedback
[C] Development of standards
[D] Development of specification
Answer: Quality control
(9) Which of the following is an example of QA?
[A] Validation
[B] Software testing
[C] Verification
[D] Documentation
Answer: Verification
(10) Which of the following option is not correct regarding QA and QC?
[A] QA depends on the activities of the entire company
[B] Process capabilities should be monitored on intermittent basis
[C] Measuring equipment’s must have a calibration certificate
[D] Normally many inspections are done during the process of manufacturing
Answer: Process capabilities should be monitored on intermittent basis
(11) Where the nodal point for National Measurement System is located?
[A] New Delhi
[B] Bombay
[C] Patna
[D] Bangalore
Answer: New Delhi
(12) Process control is carried out
[A] during production
[B] after production control
[C] before production
[D] All of the above
Answer: during production
(13) Low cost, higher volume items requires
[A] intensive inspection
[B] no inspection
[C] little inspection
[D] 100% inspection
Answer: little inspection
(14) Faults are found most cost-effectively in which test activity?
[A] design
[B] planning
[C] Check Exit criteria completion
[D] execution
Answer: planning
(15) Loop Testing methodology includes which of the following.
[A] Concatenated Loops
[B] Simple Loops
[C] Nested Loops
[D] All of the above
Answer: All of the above
(16) What happened if an expected result is not specified then
[A] it may be difficult to determine if the test has passed or failed
[B] it may difficult to repeat the test
[C] we cannot run the test
[D] we cannot automate the user input values
Answer: it may difficult to repeat the test
(17) Select which one is not an External failure costs?
[A] complaint resolution
[B] testing
[C] helpline support
[D] warranty work
Answer: testing
(18) Select the option which is not an appraisal in SQA?
[A] inter-process inspection
[B] maintenance
[C] testing
[D] quality planning
Answer: quality planning
(19) Select the people who identify the document and verifies the correctness of the software…
[A] SQA team
[B] Project team
[C] Project manager
[D] All of the mentioned
Answer: SQA team
(20) Select what is the primary objective of formal technical reviews to find during the process so that after the release of the software they do not become the defect…
[A] faults
[B] errors
[C] failure
[D] none of the mentioned
Answer: errors

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!