Home » quantitative aptitude » A and B can finish a piece of work in 30 days, B and C can finish it in 15 days, C and A in 10 days. Time taken by them together to do this work is? Quantitative aptitude A and B can finish a piece of work in 30 days, B and C can finish it in 15 days, C and A in 10 days. Time taken by them together to do this work is? July 26, 2023 48 Views QuestionA and B can finish a piece of work in 30 days, B and C can finish it in 15 days, C and A in 10 days. Time taken by them together to do this work is?Typemultiple_choiceOption5 daysincorrectOption2(1/2) daysincorrectOption7(1/2) daysincorrectOption10 dayscorrect Solution