In a detailed estimate the provision for contingencies is, usually HomeEstimation and Costing MCQsIn a detailed estimate the provision for contingencies is, usuallyQ. In a detailed estimate the provision for contingencies is, usuallyA. 1%B. 3% to 5%C. 10%D. 12% to 15%Answer: 1%
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is