The activities of a project, their duration and the precedence relationships are given in the table

Q. The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X

ActivityDuration (Weeks)Precedence Relationship
A5A
B7B
C10C
D6D
E3E
F9F
G7G
H4H
I2—-

(A) 17 (B) 21

(C) 23 (D) 25

Ans: 23

Sol:

Screenshot 717

So critical path is A – B – F – I

Critical path duration = 23 weeks