The expected out turn of 2.5 cm cement concrete floor per mansion per day

The expected out turn of 2.5 cm cement concrete floor per mansion per day

Q. The expected out turn of 2.5 cm cement concrete floor per mansion per day

A.            2.5 sqm

B.            5.0 sqm

C.            7.5 sqm

D.            10 sqm

Answer: 7.5 sqm