The expected out turn of cement concrete 1 : 2 : 4 per mason per day is HomeEstimation and Costing MCQsThe expected out turn of cement concrete 1 : 2 : 4 per mason per day isQ. The expected out turn of cement concrete 1 : 2 : 4 per mason per day isA. 5.0 m3B. 2.5 m3C. 1.5 m 3D. NoneAnswer: 5.0 m3
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is