The figure shows a pouring arrangement for casting of a metal block

The figure shows a pouring arrangement for casting of a metal block

Q. The figure shows a pouring arrangement for casting of a metal block. Frictional losses are negligible. The acceleration due to gravity is 9.81 m/s2. The time (in s, round off to two decimal places) to fill up the mold cavity (of size 40 cm ´ 30 cm ´ 15 cm) is      

 

Ans: 28.92 Sec

Sol:

Gkseries: Gkseries.com is a premier website to provide complete solution for online preparation of different competitive exams like UPSC, SBI PO, SBI clerical, PCS, IPS, IAS, IBPS PO, IBPS Clerical exam etc. & other graduate and post-graduate exams. Learn more on about us page