The maximum and minimum lead time is 4 weeks and 3 weeks respectively. If the maximum and minimum weekly consumption is 25 units and 20 units respectively, the re-ordering level will be
Q. The maximum and minimum lead time is 4 weeks and 3 weeks respectively. If the maximum and minimum weekly consumption is 25 units and 20 units respectively, the re-ordering level will be
A. 100 Units
B. 110 Units
C. 120 Units
D. 140 Units
Answer: 100 Units
Take Mock Tests
Government Schemes Mock Test | Start Test! |
Political Science Mock Test – 42 | Start Test |
History Test – 190 | Start Test |
Quantitative Aptitude Test | Start Test! | Data Interpretation - Mock Test | Start Test! |
General Awareness - Mock Test | Start Test! |
Reasoning Ability - Mock Test | Start Test! |