The maximum and minimum lead time is 4 weeks and 3 weeks respectively. If the maximum and minimum weekly consumption is 25 units and 20 units respectively, the re-ordering level will be

The maximum and minimum lead time is 4 weeks and 3 weeks respectively. If the maximum and minimum weekly consumption is 25 units and 20 units respectively, the re-ordering level will be

Q. The maximum and minimum lead time is 4 weeks and 3 weeks respectively. If the maximum and minimum weekly consumption is 25 units and 20 units respectively, the re-ordering level will be

A.            100 Units

B.            110 Units

C.            120 Units

D.            140 Units

Answer: 100 Units

Take Mock Tests

Government Schemes Mock Test Start Test!
Political Science Mock Test – 42 Start Test
History Test – 190 Start Test
Quantitative Aptitude Test Start Test!
Data Interpretation - Mock Test Start Test!
General Awareness - Mock Test Start Test!
Reasoning Ability - Mock Test Start Test!
Gkseries: Gkseries.com is a premier website to provide complete solution for online preparation of different competitive exams like UPSC, SBI PO, SBI clerical, PCS, IPS, IAS, IBPS PO, IBPS Clerical exam etc. & other graduate and post-graduate exams. Learn more on about us page