Which of the following is NOT a guideline for successfully conducting a Joint Requirements Planning (JRP) session?
A
stay on schedule
B
allow for ample breaks
C
ensure that the scribe is able to take notes
D
encourage user and management participation
E
brainstorm technical alternatives to problems identified in a JRP session
View Answer
Answer & Explanation
Answer: Option [E]