SSC CGL 2017 Tier 1 Questions and Answers

Question

A can complete a work in 20 days and B can complete the same work in 25 days. If both of them work together, then in 3 days what percent of the total work will be completed?

A 9
B 12
C 25
D 27

Answer & Explanation

Answer: [27]