Construction Planning and Management Quiz | Construction Planning and Management MCQs and Answers

81 Frederick W. Taylor introduced a system of working known as
[A] Line organisation
[B] Line and staff organisation
[C] Functional organisation
[D] Effective organisation
Answer: Functional organisation
82 The reduction in project time normally results in
[A] Decreasing the direct cost and increasing indirect cost
[B] Increasing the direct cost and decreasing the indirect cost
[C] Increasing the direct cost and indirect cost both
[D] Decreasing the direct cost and indirect cost both
Answer: Increasing the direct cost and decreasing the indirect cost

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

Article and Schedule Quiz Start Test!
83 A dummy activity
[A] Is artificially introduced
[B] Is represented by a dotted line
[C] Does not consume time
[D] All the above
Answer: All the above
84 The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
[A] 2 kg/tonne
[B] 6 kg/tonne
[C] 9 kg/tonne
[D] 20 kg/tonne
Answer: 9 kg/tonne
85 The difference between the time avail-to do a job and the time required to do the job, is known as
[A] Event
[B] Float
[C] Duration
[D] Constraint
Answer: Float
86 Frequency distribution curves
[A] Having a single lump, are called uninodal curves
[B] If symmetrical, are called normal curves
[C] If not symmetrical, are called skew curves
[D] All the above
Answer: All the above
87 In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?
[A] Yes, because of heavier overheads and handling cost
[B] Yes, because of the very high order of quality control for the factory made components
[C] No, because of repetitive manufacture of a number of elements
[D] No, because of savings in site labour
Answer: No, because of repetitive manufacture of a number of elements
88 Pick up the correct statement from the following:
[A] The difference of latest occurrence time and earliest expected time, is called slack
[B] The activities connecting the events having zero slack, lie on the critical path
[C] The critical path consumes the maximum time
[D] All the above
Answer: All the above
89 A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
[A] Reduce by 200 kg
[B] Increase by 200 kg
[C] Increase by 250 kg
[D] Reduce by 250 kg
Answer: Reduce by 200 kg
90 A construction schedule is prepared after collecting
[A] Number of operations
[B] Output of labour
[C] Output of machinery
[D] All the above
Answer: All the above
91 Which of the following is not a PERT event?
[A] Site investigation started
[B] Sessional work completed
[C] Bus starts from Jaipur
[D] Class is being attended
Answer: Class is being attended
92 Mile Stone charts were invented in the year of
[A] 1910
[B] 1920
[C] 1930
[D] 1940
Answer: 1940
93 Whenever an activity has zero total float, then
[A] Free float of the activity must be zero but independent float need not be zero
[B] Independent float must be zero but free float need not be zero
[C] Free float and independent float both must be zero
[D] Free float and independent float both need not be zero
Answer: Free float and independent float both must be zero
94 Final technical authority of a project lies with
[A] Assistant Engineer
[B] Executive Engineer
[C] Superintending Engineer
[D] Chief Engineer
Answer: Chief Engineer
95 Slack time refers to
[A] An activity
[B] An event
[C] Both event and activity
[D] None of the above
Answer: An event
96 While scheduling a project by C.P.M.
[A] A project is divided into various activities
[B] Required time for each activity is established
[C] Net work is drawn by connecting the activities and the events
[D] All the above
Answer: All the above
97 The main disadvantage of line organisation, is
[A] Rigid structure
[B] Extraordinary delay in communications
[C] Top level executions over work
[D] All the above
Answer: All the above
98 Which one of the following is not an excavating and moving type of equipment?
[A] Bulldozer
[B] Clam shell
[C] Scraper
[D] Dump truck
Answer: Dump truck
99 The first method invented for planning projects, was
[A] Bar chart method
[B] Milestone chart
[C] Critical path method (CPM)
[D] Programme Evaluation and Review Technique (PERT)
Answer: Bar chart method
100 The salient feature of functional organisation is
[A] Strict adherence to specifications
[B] Separation of planning and design part
[C] Each individual maintains functional efficiency
[D] All the above
Answer: All the above

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!

Latest Test Series

CLICK HERE TO VIEW ALL COURSES