Construction Planning and Management Quiz | Construction Planning and Management Objective Type Questions and Answers

(21) Pick up the correct statement from the following:
[A] The float may be positive, zero or negative
[B] If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
[C] If the float of an activity is negative, delay in its performance is bound to delay the completion of project
[D] All the above
Answer: All the above
(22) PERT technique of network analysis is mainly useful for
[A] Small projects
[B] Large and complex projects
[C] Research and development projects
[D] Deterministic activities
Answer: Research and development projects

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

Article and Schedule Quiz Start Test!
(23) The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
[A] Event
[B] Free float
[C] Dummy
[D] Constraint
Answer: Dummy
(24) Select the incorrect statement.
[A] Start float and finish float are always equal.
[B] Total float can be either start float or finish float.
[C] Start float and finish float need not be equal.
[D] Start float and finish float are the differences between activity times and not event times.
Answer: Start float and finish float need not be equal.
(25) Construction team means
[A] An engineer
[B] An architect
[C] An owner
[D] All the above
Answer: All the above
(26) The time corresponding to minimum total project cost is
[A] Crash time
[B] Normal time
[C] Optimistic time
[D] Between normal time and crash time
Answer: Between normal time and crash time
(27) Bar charts are suitable for
[A] Minor works
[B] Major works
[C] Large projects
[D] All the Above
Answer: Minor works
(28) For a given size of bucket, the ideal output of a dragline will be least in
[A] Moist loam
[B] Sand and gravel
[C] Good common earth
[D] Wet sticky clay
Answer: Wet sticky clay
(29) Power stations are generally treated as
[A] Light construction
[B] Heavy construction
[C] Industrial construction
[D] Electrical construction
Answer: Industrial construction
(30) If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
[A] 2.3% and 84.1%
[B] 97.7% and 84.1%
[C] 97.7 % and 15.9%
[D] 15.9% and 97.7%
Answer: 2.3% and 84.1%
31 A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is
[A] 10000 kg
[B] 12500 kg
[C] 22500 kg
[D] 5000 kg
Answer: 12500 kg
32 Pick up the incorrect statement from the following:
[A] The various functions under each activity, are shown by one bar on Bar Charts
[B] Bar chart establishes the interdependency of one event on another
[C] Only approximate percentage of the completed work is reported
[D] None of these
Answer: Bar chart establishes the interdependency of one event on another
33 While filling the tender for any work, the contractor considers
[A] Site survey
[B] Availability of construction materials
[C] Availability of labour
[D] All the above
Answer: All the above
34 Interfering float is the difference between
[A] Total float and free float
[B] Total float and independent float
[C] Free float and independent float
[D] None of the above
Answer: Total float and free float
35 The time with which direct cost does not reduce with the increase in time is known as
[A] Crash time
[B] Normal time
[C] Optimistic time
[D] Standard time
Answer: Normal time
36 A golden rule for the procurement of construction stones, suggests
[A] 100% at the site
[B] 67% at the site and 33% under procurement
[C] 50% at the site and 50% under procurement
[D] 33% at the site and 67% under procurement
Answer: 67% at the site and 33% under procurement
37 In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
[A] Longest duration
[B] Highest cost slope
[C] Least cost slope
[D] Shortest duration
Answer: Least cost slope
38 Pick up the correct statement from the following:
[A] Optimistic time estimate refers to activities
[B] Pessimistic time estimate refers to activities
[C] Most likely time estimate refers to activities
[D] All the above
Answer: All the above
39 The independent float affects only
[A] Preceding activities
[B] Succeeding activities
[C] The particular activity involved
[D] None of the above
Answer: The particular activity involved
40 Site order book is used for recording
[A] Instructions by the executive engineers
[B] Construction measurements
[C] Issue of store equipments
[D] Names of the casual labour
Answer: Instructions by the executive engineers

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!

Latest Test Series

SSC CGL

Start Test 1000+ Tests Latest patternView Course

DELHI POLICE SI

Start Test 1000+ Tests Latest patternView Course

WEST BENGAL PSC

Start Test 1000+ Tests Latest patternView Course

CISF CONSTABLE

Start Test 1000+ Tests Latest patternView Course

JAIIB

Start Test 30 Full Length Tests View Course

ADRE 2024

Start Test 25000+ QUESTIONS SOLUTIONSView Course

RRB RRC GROUP D

Start Test 15000+ QUESTIONS Latest patternView Course

UP POLICE SI

Start Test 16000+ QUESTIONS Latest patternView Course
CLICK HERE TO VIEW ALL COURSES