Construction Planning and Management Quiz | Construction Planning and Management MCQs with Answers

101 Completion of an activity on CPM network diagram, is generally known
[A] Event
[B] Node
[C] Connector
[D] All the above
Answer: All the above
102 The process of incorporating changes and rescheduling or replanning is called
[A] Resource levelling
[B] Resource smoothening
[C] Updating
[D] Critical path scheduling
Answer: Updating

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

Article and Schedule Quiz Start Test!
103 Pick up the incorrect statement from the following:
[A] An activity of a project is denoted by an arrow on the net work
[B] The tail of the arrow indicates the start of the activity
[C] The head of the arrow indicates the end of the activity
[D] The arrows are drawn to scale from left to right
Answer: The arrows are drawn to scale from left to right
104 Pick up the PERT event from the following:
[A] Digging of foundation started
[B] Digging of foundation completed
[C] Laying of concrete started
[D] All the above
Answer: All the above
105 Mobilization advance up to 10% of the cost of work is given to a contractor
[A] On commencement of work at site for payment of loan taken by him
[B] For the purchase of construction materials
[C] For the payment of advances to labour and other staff
[D] For all activities required to start the work at site on finalization of the contract document
Answer: For all activities required to start the work at site on finalization of the contract document
106 Military organisation is known as
[A] Line organisation
[B] Line and staff organisation
[C] Functional organisation
[D] None of these
Answer: Line organisation
107 Residential buildings are treated as
[A] Light construction
[B] Heavy construction
[C] Industrial construction
[D] Private construction
Answer: Light construction
108 Critical path
[A] Is always longest
[B] Is always shortest
[C] May be longest
[D] May be shortest
Answer: Is always longest

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!

Latest Test Series

CLICK HERE TO VIEW ALL COURSES