JOIN ADRE 2.0 Telegram Group

Switchgear and Protection Quiz | Switchgear and Protection Objective Type Questions and Answers

Questions
21 Induction cup relay is operated due to changes in
A Current
B Voltage
C Impedance
D All Of The Above

Answer: All Of The Above
22 Which of the following statements is incorrect ?
A Lightning arrestors are used before the switchgear
B Shunt reactors are used as compensation reactors
C The peak short current is (1.8 xV2) times the A.C. component
D The MVA at fault is equal to base MVA divided by per unit equivalent fault reactance

Answer: Lightning arrestors are used before the switchgear
Advertisement
Article and Schedule Quiz Start Test!

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

23 Bus coupler is very essential in arrangement
A Single Bus
B Double Bus, Double Breaker
C Main And Transfer Bus
D None of the above

Answer: Main And Transfer Bus
24 For cost and safety, the outdoor substations are installed for voltages above
A 11 kV
B 33 kV
C 60kV
D 110kV

Answer: 33 kV
25 Distance relays are generally
A Split-Phase Relays
B Reactance Relays
C Impedance Relays
D None Of The Above

Answer: None Of The Above
26 A _______ is used to measure the stator % winding temperature of the generator.
A Thermocouple
B Pyrometer
C Resistance Thermometer
D Thermometer

Answer: Resistance Thermometer
27 The relay with inverse time characteristic will operate within
A 1.5 sec
B 5 to 10 sec
C 5 to 20 sec
D 20 to 30 sec

Answer: 5 to 10 sec
28 Which of the following devices will receive voltage surge first travelling on the transmission line ?
A Lightning arresters
B Relays
C Step-down transformer
D Switchgear

Answer: Lightning arresters
29 Series reactors should have
A low resistance
B high resistance
C low impedance
D All Of The Above

Answer: low resistance
30 Arc in a circuit breaker is interrupted at
A zero current
B maximum current
C minimum voltage
D maximum voltage

Answer: zero current
31 What will be the reflection co-efficient of the wave of load connected to transmission line if surge impedance of the line is equal to load ?
A Zero
B Unity
C Infinity
D None of the above

Answer: Zero
32 Over voltage protection is recommended for
A hydro-electric generators
B steam turbine generators
C gas turbine generators
D all of the above

Answer: all of the above
33 Overfluxing protection is recommended for
A distribution transformer
B generator transformer of the power plant
C auto-transformer of the power plant
D station transformer of the power plant

Answer: generator transformer of the power plant
34 Admittance relay is _______ relay.
A Impedance
B Directional
C Non-Directional
D None Of The Above

Answer: Directional
35 The material used for fuse must have
A low melting point and high specific resistance
B low melting point and -low specific resistance
C high melting point and low specific resistance
D low melting point and any specific resistance

Answer: low melting point and high specific resistance
36 The steady state stability of the power system can be increased by
A connecting lines in parallel
B connecting lines in series
C using machines of high impedance
D all of the above

Answer: connecting lines in parallel
37 A fuse is connected
A either in series or in parallel with circuit
B in parallel with circuit
C in series with circuit
D None Of The Above

Answer: in series with circuit
38 A fuse is never inserted in
A neutral wire
B negative of D.C. circuit
C positive of D.C. circuit
D None Of The Above

Answer: neutral wire
39 A switchgear is device used for
A interrupting an electrical circuit
B switching an electrical circuit 111
C switching and controlling an electrical circuit
D switching, controlling and protecting the electrical circuit and equipment

Answer: interrupting an electrical circuit
40 By which of the following methods major portion of the heat generated in a H.R.C. fuse is dissipated ?
A Radiation
B Convection
C Conduction
D None Of The Above

Answer: Conduction

ADRE 2.0 FULL LENGTH MOCK TEST

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!
Advertisement
Assam Direct Recruitment Test Series