JOIN ADRE 2.0 Telegram Group

Project Management Exam Questions and Answers | Project Management MCQs

Questions
1 The probability of completing the project can be estimated based upon the ____ .
A Uniform distribution curve
B Normal distribution curve.
C U-shaped distribution curve
D None of the above

Answer:Normal distribution curve.
2 In the initial stage of the project the probability of completing the project is ___ .
A Zero
B High
C Low
D Any of the above

Answer: Low
Advertisement
Article and Schedule Quiz Start Test!

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

3 The entire process of a project may be considered to be made up on number of sub process placed in different stage called the
A Technical key resources
B Work key structure
C Work Breakdown Structure (WBS).
D None of the above

Answer: Work Breakdown Structure (WBS).
4 Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known.
A Algorithmic model
B Expert judgment
C Top down
D Analogy

Answer: Analogy
5 Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job.
A Algorithmic model
B Expert judgment
C Bottom-up
D Top down

Answer:Bottom-up
6 Following is (are) the component(s) of risk management
A Risk Assessment
B Risk Control
C Risk Ranking
D All of the above

Answer: All of the above
7 Following are the characteristics of Project Mindset.
A Time, Responsiveness, Information sharing, Processes, structured planning
B Time, Project management, Information sharing, Processes, structured planning
C Time, Responsiveness, Information sharing, capability, structured planning
D Time, Responsiveness, Information sharing, Processes, project planning

Answer:Time, Responsiveness, Information sharing, Processes, structured planning
8 “Devising and maintaining a workable scheme to accomplish the business need” is
A Initiating process
B Planning process
C Executing process
D Controlling process

Answer: Planning process
9 Controlling the changes in the project may affect
A The progress of the project
B Stage cost
C Project scope
D All of the above

Answer: All of the above
10 Following is (are) the tool(s) for changing a process
A Change Management System (CMS)
B Configuration Management (CM)
C Both (A) and (B)
D None of the above

Answer:Both (A) and (B)

ADRE 2.0 FULL LENGTH MOCK TEST

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!
Advertisement
Assam Direct Recruitment Test Series