37. Generally the PERT technique deals with the project of ____________
  • [A] Repetatative nature.
  • [B] Non-repetative nature.
  • [C] Determinstic nature.
  • [D] None of the above.

Answer: Option [B]

38. While drawing the network diagram for each activity project we should look __________
  • [A] What acitivities preceede this acitivity
  • [B] What acitivities follow this acitivity.
  • [C] What activity can concurrently take place with this activity.
  • [D] All the above.

Answer: Option [D]

Advertisement
Article and Schedule Quiz Start Test!

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

39. Float or slack analysis is useful for __________
  • [A] Projects behind the schedule only.
  • [B] Projects ahead of the schedule only.
  • [C] Both (A) & (B)
  • [D] None of the above.

Answer: Option [A]

40. Activity –on-arrow (AOA) diagram is prefeered over Activity –on-node (AON) diagram because __________
  • [A] AOA diagrams are simple to construct
  • [B] AOA diagrams give a better sense of the flow of time throughout a project.
  • [C] AOA diagrams do not involve dummy activites
  • [D] AOA diagrams do not involve dummy activites

Answer: Option [B]

41. Crashing is the process of reducing the total time that it takes to complete a project by expanding ___________
  • [A] Additional funds.
  • [B] No.of.days
  • [C] Both (A) & (B)
  • [D] None of the above

Answer: Option [A]

42. ___________ is the time consuming job (or) task that is a key subpart of the total project
  • [A] Activity.
  • [B] Event.
  • [C] Node.
  • [D] All the above

Answer: Option [A]

43. Network is the graphical display of a project that contains both ______ and _________
  • [A] Activities and events.
  • [B] Activities and dummy activities.
  • [C] Both (A) & (B).
  • [D] Neither (A) nor (B).

Answer: Option [A]

44. Latest finish time that an activity can be finished without _______ the entire project.
  • [A] Delaying.
  • [B] Planning
  • [C] Both (A) & (B)
  • [D] None of the above

Answer: Option [A]

45. PERT is a tool for __________ and control time
  • [A] Delaying.
  • [B] Planning.
  • [C] Both (A) & (B)
  • [D] None of the above

Answer: Option [B]

46. Project __________ phase allocates resources to work packages
  • [A] Planning.
  • [B] Scheduling.
  • [C] Controlling.
  • [D] Both (B) & (C).

Answer: Option [A]

47. A __________ is an endeavour to create a unique product service.
  • [A] Project.
  • [B] Network.
  • [C] Activity.
  • [D] Node.

Answer: Option [A]

48. In Transportation problem the preferred method of obtaining either optimal or very close to the optimal solution is _____________.
  • [A] north west corner rule.
  • [B] east cost method.
  • [C] vogel’s approximation method.
  • [D] simplex method.

Answer: Option [C]

ADRE 2.0 FULL LENGTH MOCK TEST

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!
Advertisement
Assam Direct Recruitment Test Series