Construction Planning and Management Quiz | Construction Planning and Management MCQs and Answers

Questions
81 Frederick W. Taylor introduced a system of working known as
A Line organisation
B Line and staff organisation
C Functional organisation
D Effective organisation

Answer: Functional organisation
82 The reduction in project time normally results in
A Decreasing the direct cost and increasing indirect cost
B Increasing the direct cost and decreasing the indirect cost
C Increasing the direct cost and indirect cost both
D Decreasing the direct cost and indirect cost both

Answer: Increasing the direct cost and decreasing the indirect cost
Advertisement
Article and Schedule Quiz Start Test!

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

83 A dummy activity
A Is artificially introduced
B Is represented by a dotted line
C Does not consume time
D All the above

Answer: All the above
84 The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
A 2 kg/tonne
B 6 kg/tonne
C 9 kg/tonne
D 20 kg/tonne

Answer: 9 kg/tonne
85 The difference between the time avail-to do a job and the time required to do the job, is known as
A Event
B Float
C Duration
D Constraint

Answer: Float
86 Frequency distribution curves
A Having a single lump, are called uninodal curves
B If symmetrical, are called normal curves
C If not symmetrical, are called skew curves
D All the above

Answer: All the above
87 In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?
A Yes, because of heavier overheads and handling cost
B Yes, because of the very high order of quality control for the factory made components
C No, because of repetitive manufacture of a number of elements
D No, because of savings in site labour

Answer: No, because of repetitive manufacture of a number of elements
88 Pick up the correct statement from the following:
A The difference of latest occurrence time and earliest expected time, is called slack
B The activities connecting the events having zero slack, lie on the critical path
C The critical path consumes the maximum time
D All the above

Answer: All the above
89 A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
A Reduce by 200 kg
B Increase by 200 kg
C Increase by 250 kg
D Reduce by 250 kg

Answer: Reduce by 200 kg
90 A construction schedule is prepared after collecting
A Number of operations
B Output of labour
C Output of machinery
D All the above

Answer: All the above
91 Which of the following is not a PERT event?
A Site investigation started
B Sessional work completed
C Bus starts from Jaipur
D Class is being attended

Answer: Class is being attended
92 Mile Stone charts were invented in the year of
A 1910
B 1920
C 1930
D 1940

Answer: 1940
93 Whenever an activity has zero total float, then
A Free float of the activity must be zero but independent float need not be zero
B Independent float must be zero but free float need not be zero
C Free float and independent float both must be zero
D Free float and independent float both need not be zero

Answer: Free float and independent float both must be zero
94 Final technical authority of a project lies with
A Assistant Engineer
B Executive Engineer
C Superintending Engineer
D Chief Engineer

Answer: Chief Engineer
95 Slack time refers to
A An activity
B An event
C Both event and activity
D None of the above

Answer: An event
96 While scheduling a project by C.P.M.
A A project is divided into various activities
B Required time for each activity is established
C Net work is drawn by connecting the activities and the events
D All the above

Answer: All the above
97 The main disadvantage of line organisation, is
A Rigid structure
B Extraordinary delay in communications
C Top level executions over work
D All the above

Answer: All the above
98 Which one of the following is not an excavating and moving type of equipment?
A Bulldozer
B Clam shell
C Scraper
D Dump truck

Answer: Dump truck
99 The first method invented for planning projects, was
A Bar chart method
B Milestone chart
C Critical path method (CPM)
D Programme Evaluation and Review Technique (PERT)

Answer: Bar chart method
100 The salient feature of functional organisation is
A Strict adherence to specifications
B Separation of planning and design part
C Each individual maintains functional efficiency
D All the above

Answer: All the above

ADRE 2.0 FULL LENGTH MOCK TEST

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!
Advertisement
Assam Direct Recruitment Test Series