Construction Planning and Management Quiz | Construction Planning and Management Multiple Choice Questions with Answers

Questions
61 Select the incorrect statement.
A Earliest start of an activity is the early event time of the node it leaves.
B Latest finish of an activity is the late event time of the node it enters.
C Latest start of an activity is its latest finish minus its duration.
D None of the above

Answer: None of the above
62 In the given figure, the network of a project represents
A Activity of an excavation of a footing
B Activity of an excavation which starts at event No. 1 and ends at even No. 2
C Activity of excavation which takes 8 units of time
D None of these

Answer: Activity of excavation which takes 8 units of time
Advertisement
Article and Schedule Quiz Start Test!

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

63 Economic saving of time results by crashing
A Cheapest critical activity
B Cheapest noncritical activity
C Costliest critical activity
D Costliest noncritical activity

Answer: Cheapest critical activity
64 Time and progress chart of a construction, is also known as
A Bar chart
B Gantt chart
C Modified Mile stone chart
D All the above

Answer: All the above
65 If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
A 500 cum
B 1000 cum
C 1500 cum
D 2000 cum

Answer: 500 cum
66 Pick up the correct statement from the following:
A Programme Evaluation and Review Technique, is event oriented
B Programme Evaluation and Review Technique is not event oriented
C Critical Path Method is event oriented
D Critical Path method is event oriented

Answer: Programme Evaluation and Review Technique, is event oriented
67 The basic action involved in sheep foot rolling is
A Kneading
B Pressing
C Tamping
D Vibration

Answer: Kneading
68 Consider the following operations:

1. Drilling

2. Blasting

3. Mucking

4. Placing steel

5. Placing concrete

The correct sequence of these operations in tunnel construction is
A 1, 2, 4, 3, 5
B 1, 3, 2, 4, 5
C 1, 2, 3, 4, 5
D 1, 3, 4, 2, 5

Answer: 1, 2, 3, 4, 5
69 Pick up the correct statement from the following:
A Earliest expected time is denoted by TE
B Latest occurrence time is denoted by TL
C Contractual obligation time is denoted by Ts
D All the above

Answer: All the above
70 If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
A 4 days
B 6 days
C 10 days
D 16 days

Answer: 16 days
71 The main principle of an organisation, is
A Unity of command
B Effective control at all levels
C Delegation of authority
D All the above

Answer: All the above
72

Assertion (A): Activity 57 is critical.

Reason (R): Earliest finish time and latest finish time for events 57 are same

Select the correct answer.
A A is correct but R is not correct
B R is correct but A is not correct
C Both A and R is correct
D Both A and R is incorrect

Answer: A is correct but R is not correct
73 Pick up the incorrect statement from the following:
A The activity is the time consuming part of a project
B The beginning and end of a job, are called events
C The activity which consumes maximum time, is called a node
D Logically and sequentially connected activities and events form a network

Answer: The activity which consumes maximum time, is called a node
74 Total float for any activity is defined as the difference between
A Its latest finish time and earliest start time for its successor activity
B Its latest start time and earliest start time
C Its latest start time and earliest finish time
D Its earliest finish time and earliest start time for its successor activity

Answer: Its latest start time and earliest start time
75 If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
A EF = ES + D
B LS = LF - D
C LF = LS + D
D All the above

Answer: All the above
76 Select the correct statement.
A Activity arrows in a CPM network are drawn to scale
B The tail of an arrow represents the finish of an activity
C Arrow bead represents the start of an activity
D None of the above

Answer: None of the above
77 Various activities of a project, are shown on bar charts by
A Vertical lines
B Horizontal lines
C Dots
D Crosses

Answer: Horizontal lines
78 If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
A 3.5 and 5/6
B 5 and 25/36
C 3.5 and 25/36
D 4 and 5/6

Answer: 3.5 and 25/36
79 The object of technical planning, is
A Preparation of specifications
B Preparation of estimates
C Initiating the procurement action of resources
D All the above

Answer: All the above
80 The technique for establishing and maintaining priorities among the various jobs of a project, is known
A Event flow scheduling technique
B Critical ratio scheduling
C Slotting technique for scheduling
D Short interval scheduling

Answer: Critical ratio scheduling

ADRE 2.0 FULL LENGTH MOCK TEST

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!
Advertisement
Assam Direct Recruitment Test Series