Estimation and Costing MCQs | Estimation and Costing Multiple Choice Questions with Answers

Questions
61 Pick up the correct statement from the following:
A The bending of bars near supports is generally at 45°
B The bent up bars at a support resist the sharing force
C The bent up bars at a support resist the negative bending moment
D All the above

Answer: All the above
62 The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is
A (6 + 12) chains
B (6 + 18) chains
C (6 + 15) chains
D None of these

Answer: (6 + 12) chains
Advertisement
Article and Schedule Quiz Start Test!

DOWNLOAD CURRENT AFFAIRS PDF FROM APP

63 Pick up the correct statement from the following:
A All pipes are measured along the centre line of the pipes in metres
B All pipes and fittings are classified according to their diameters
C The diameter of the pipes is the nominal diameter of internal bore
D All the above

Answer: All the above
64 Pick up the correct statement in case of water supply.
A Pipes are classified according to their sizes and quality
B Cutting through walls and floors are included with the item
C Pipes laid in trenches and pipes fixed to walls are measured separately
D All the above

Answer: All the above
65 The total length of a cranked bar through a distance D. at 45° in case of a beam of effective length L, is
A L + (2 × 0.42 d)
B L – (0.42 d)
C L – (2 × 0.4 d)
D L + 0.42 d

Answer: L + (2 × 0.42 d)
66 If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is
A Bd + Sd2
B ½ (Bd + Sd2)
C B × d – Sd1/2
D B + d + Sd

Answer: Bd + Sd2
67 The minimum width of a septic tank is taken
A 75 cm
B 90 cm
C 70 cm
D 80 cm

Answer: 75 cm
68 For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is
A 0.274 m3
B 0.247 m3
C 0.200 m3
D None of the above

Answer: 0.274 m3

ADRE 2.0 FULL LENGTH MOCK TEST

Take Mock Tests

Missiles Mock Test Start Test!
SSC MTS Mock Test Start Test
IBPS CLERK MOCK TEST Start Test
SSC MTS 2022 JULY 26 Shift 1 (ENGLISH) Start Test!
SSC GD Previous Year Paper 2021 Nov 17 Shift - I (Hindi) Start Test!
SSC CGL Tier - 1 PYP 2022 April 21 Shift- 1 (ENGLISH) Start Test!
MPSC PAPER I MOCK TEST 1 (ENGLISH) Start Test!
IB Security Assistant Mock test 1 (english) Start Test!
UP POLICE CONSTABLE MOCK TEST 1 Start Test!
DELHI POLICE CONSTABLE MOCK TEST 1 (HINDI) Start Test!
Advertisement
Assam Direct Recruitment Test Series