(1) __________________ calculates the timing and quantities of material orders needed to support the master schedule.
[A] Sale and operations planning
[B] Distribution requirements planning
[C] Material requirements planning
[D] Master production schedule
Answer: Material requirements planning
(2) Which of the following lot-sizing techniques is likely to prove the most complex to use?
[A] Part period balancing (PPB)
[B] The Wagner-Whitin algorithm
[C] Economic order quantity (EOQ)
[D] Lot-for-lot
Answer: The Wagner-Whitin algorithm
(3) __________________ is a time phased approach to managing the physical distribution environment with dependent demand logic.
[A] Master production schedule
[B] Distribution requirements planning
[C] Sale and operations planning
[D] Material requirements planning
Answer: Distribution requirements planning
(4) The list of quantities of components, ingredients, and materials required to produce a product is the
[A] Bill-of-materials.
[B] Engineering change notice.
[C] Purchase order.
[D] Master schedule.
Answer: Bill-of-materials.
(5) When a bill-of-materials is used in order to assign an artificial parent to a bill-of-materials, it is usually called a
[A] Phantom bill-of-materials.
[B] Planning bill-of-materials.
[C] Modular bill-of-materials.
[D] Pick list.
Answer: Planning bill-of-materials.
(6) __________________ can be seen as the amount of new inventory created by production.
[A] Scheduled receipts
[B] Gross requirements
[C] Planning horizon
[D] Available to promise
Answer: Available to promise
(7) A lot-sizing technique that generates exactly what was required to meet the plan is
[A] The Wagner-Whitin algorithm.
[B] Economic order quantity.
[C] Lot-for-lot.
[D] Part period balancing.
Answer: Lot-for-lot.
(8) The operations manager has several tools available to deal with MRP system nervousness. Those tools are
[A] Pseudo bills and kits.
[B] Time fences and pegging.
[C] Buckets with back flush.
[D] Net and gross requirements.
Answer: Time fences and pegging.
(9) ___________________ is the amount of materials necessary to support production of the required output in the next higher level in the bill of materials.
[A] Planning horizon
[B] Available to promise
[C] Net requirements
[D] Gross requirements
Answer: Gross requirements
(10) Breaking up the order and running part of it ahead of schedule is known as
[A] Operations splitting.
[B] Lot splitting.
[C] Pegging.
[D] Overlapping.
Answer: Lot splitting.